Project RERA record · Mumbai, Thane & the MMR

Olympia C D

by Nirmal Developers · MahaRERA P51800012383 · Certificate Signed · declared completion Dec 2025

Not filing quarterly progress reports

Not filing quarterly progress reports. Mumbai Suburban · Mulund West

Not filing quarterly progress reports

The developer is not filing the legally required quarterly progress reports with MahaRERA. This is a compliance violation and makes it impossible to independently track construction progress through the regulator.

Olympia C D is on MahaRERA's non-compliance list for not filing quarterly progress reports. RERA requires developers to report construction progress and sales data to the regulator each quarter — the absence of filings means construction status cannot be independently verified through MahaRERA's public register.

On the regulator's record

  • 34 quarterly reporting periods on MahaRERA's compliance schedule — 34 flagged for QPR default, currently in default on QPR filings
  • 9 litigation cases on MahaRERA's record for this project
  • 92 complaints filed with MahaRERA against this project

Source: MahaRERA public project record.

Other RERA-registered projects in Mulund West

A AND O Excellente
Riddhi Siddhi Corporation
AAI Satidevi Paradise
Shreenath Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Request the report on Olympia C D

We analyse Olympia C D in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Free · Risk Snapshot + alerts

The regulatory risk spine for Olympia C D, emailed as a clean scorecard — plus an alert if the RERA status changes:

  • 🔴  Not filing quarterly progress reports

Something went wrong — email hello@quietlist.in.

✓ On its way to your inbox — plus alerts if the status changes.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Jul 2026