Mumbai/Project record

MahaRERA · the public record

Sai Empire

Lodha Heaven, Nilaje, Dombivali East · Om Sai Associates

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2023declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for Sai Empire

MahaRERA · P51700027195

Delivery and registration

When is the project declared for completion?

Sai Empire is registered with MahaRERA as P51700027195 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

40months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP51700027195
Registered on24 Nov 2020
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 40 months past the declared date

Promoter record

What else is this promoter on record for?

Om Sai Associates is the promoter of record on 5 projects registered with MahaRERA.

5projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 19 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sai Empire in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Sai Empire1G+731 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Jun 20241. Due to market conditions the disbursement from customers was very low. Due to funds problems the work completed was slow as compared to what we have predicted at the time of RER

Location, Land & Connectivity

Located at Lodha Heaven, Nilaje, Dombivali East, Near Bank of Baroda, Kalubai Chowk, Kalyan, Thane, 421204. Per the filed land record, the plot is bounded to the north by Way to Lodha Group, to the south by Wall, to the east by Gajanan Patil Plot and to the west by Subhash Patil Plot. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dombivali

Alimkar Heights
declared completion Oct 2026 · Alimkar & Sons
Neelkamal Residency AND Business Park
declared completion Dec 2026 · Neelkamal Buildco
Paramount
declared completion Dec 2026 · Metro Dream Homes
Auroville Wing C AND D
declared completion Dec 2026 · Arya Construction
Avasar Pride
Not filing quarterly progress reports · declared completion Dec 2026 · D P Realty
Balaji Estate Phase 2
declared completion Dec 2026 · M/S SAI Balaji Buildcon
More builders in Dombivali

Major developers building in Dombivali

More projects in Thane

Other RERA-registered projects in Thane

Sai Empire
declared completion Dec 2027 · M/s Sai Shakti Associates
SAI Enclave
declared completion Dec 2026 · Sairajdevelop
SAI Enclave
declared completion Jun 2028 · SAI Samarth Construction
SAI Enclave Wing B
declared completion Dec 2026 · Mehta Realty
SAI Flora
declared completion Jun 2028 · SAI RAJ Developers
Sai Flora
declared completion Dec 2026 · M/S Mitra Reality

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.