Mumbai/Project record

MahaRERA · the public record

SHREE BALAJI DEVELOPERS

SHAKARA NAGAR · SHREE BALAJI DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
01 Apr 2026declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for SHREE BALAJI DEVELOPERS

MahaRERA · P51700026996

Delivery and registration

When is the project declared for completion?

SHREE BALAJI DEVELOPERS is registered with MahaRERA as P51700026996 and the promoter has declared completion for 01 Apr 2026.

01 Apr 2026

declared completion

6months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700026996
Registered on10 Nov 2020
Promoter-declared completion01 Apr 2026
Current statusCertificate Signed
Against todayabout 6 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREE BALAJI DEVELOPERS record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Promoter record

What else is this promoter on record for?

SHREE BALAJI DEVELOPERS is the promoter of record on 22 projects registered with MahaRERA.

22projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREE BALAJI DEVELOPERS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
VINAYAK VYOM COMPLEX A B C D WING1G+901 Oct 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at SHAKARA NAGAR, KALYAN SHIL ROAD, Kalyan, Thane, 421204. Per the filed land record, the plot is bounded to the north by SHANKARA FARMCY COLLAGE, to the south by BALARAM KASHYAP PATIL LAND, to the east by RATNABAI S MHATRE LAND and to the west by S NO 88 H NO 1 LAND. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Shree Balaji Developers project & its RERA track record →

Other RERA-registered projects in Dombivali

Alimkar Heights
declared completion Oct 2026 · Alimkar & Sons
Neelkamal Residency AND Business Park
declared completion Dec 2026 · Neelkamal Buildco
Paramount
declared completion Dec 2026 · Metro Dream Homes
Auroville Wing C AND D
declared completion Dec 2026 · Arya Construction
Avasar Pride
Not filing quarterly progress reports · declared completion Dec 2026 · D P Realty
Balaji Estate Phase 2
declared completion Dec 2026 · M/S SAI Balaji Buildcon
More builders in Dombivali

Major developers building in Dombivali

More projects in Thane

Other RERA-registered projects in Thane

Shree Balaji Developers
declared completion Apr 2024 · Shree Balaji Developers
Shree Balaji Developers
declared completion Dec 2024 · Shree Balaji Developers
Shree Balaji Empire
declared completion Dec 2030 · Shubham Housing
Shree Balajis Srushtee
declared completion Jun 2022 · Shree Bajali Builders AND Developers
Shree Ballaleshwar
declared completion Dec 2028 · M/S Patil Associates
Shree Builders AND Developers
declared completion Nov 2022 · M/S Shree Builders AND Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 11 Sep 2026. Document and inventory dates are shown in their sections.