Bangalore/Project record

K-RERA · the public record

ADI'S NORTH LAKE

Bengaluru North · ADI DEVELOPERS

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
30 Sep 2018declared completionK-RERA registration · read 25 Oct 2026
135registered unitsK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Registered units and project size

Two and Three BHK Flats
30

Filed categories, unchanged · K-RERA registration · read 25 Oct 2026

The whole registration

1.4registered acres

93.4registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for ADI'S NORTH LAKE

K-RERA · PRM/KA/RERA/1251/309/PR/171030/000993

Project facts and comparisons

On the register

Declared completion30 September 2018
Land area5,849 sq m (1.4 acres)
Homes registered135
Tower/wing entries1
Unit mix30 × Two and Three BHK Flats

In context

Density93.4 homes per acre
Density in context73rd percentile of 529 Bengaluru North projects (median 75.3)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units135Total inventory registered with K-RERA.
Official carpet area4,000 sqmTotal carpet area reported for the project.
Registered land area5,849 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)149Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date22-12-2014

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Two and Three BHK Flats30100%4,000 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Adi's North Lake4135149-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 135 official flat/unit rows, matching the 135 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK93734.0-953.0 sqft400.0 sqft93
3BHK421,068.0-1,114.0 sqft450.0 sqft43

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Adi's North Lake135734.0-1,114.0 sqft400.0-450.0 sqft136
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
101Adi's North Lake02BHK734.0 sqft400.0 sqft1
102Adi's North Lake02BHK848.0 sqft400.0 sqft1
103Adi's North Lake02BHK919.0 sqft400.0 sqft1
104Adi's North Lake03BHK1,068.0 sqft450.0 sqft1
105Adi's North Lake03BHK1,068.0 sqft450.0 sqft1
106Adi's North Lake03BHK1,068.0 sqft450.0 sqft1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

Litigation status was not supplied in the captured record. This is not confirmation that there are no cases.

6 of 15 compliance document slots are filed as Not Applicable; the remaining 9 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Sep 2018 — which has passed with no OC on file.

Approval documents

Electricity (BESCOM/ESCOM)Not identified in the document list
Water & sewage (BWSSB/KWSSB)Not identified in the document list
Fire NOCNot identified in the document list
Pollution control (KSPCB)Not identified in the document list
Environmental clearanceNot identified in the document list
Airport Authority height clearanceNot identified in the document list

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

K-RERA complaint orders (30 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
sawaji varun vs ADI DEVELOPERSBWSSB Connection needs to complete and legal handover of the project to the associationAUTHORITY30/07/2025
YOGESH MOHAN PONDICHERY vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
VIKASH PRASAD vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
Kishorekumar vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
ARUNA vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
Atit Kulkarni vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
VARUN NAIR vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
Maneesh Sanwal vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
Basavaraj vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
anil pachauri vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of associationAUTHORITY30/07/2025
Thillai chidambaram P vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
Rameshchandra pathak vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
Pavan kumar Lohumi vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
Gopi G vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
Roshan Mathews Cahndy vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
Mohammed Imdadul Ahmed vs ADI DEVELOPERSIn the coCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
Vipin Nambiar vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
T DASARADA RAM vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association and properly aligned as per approved government planAUTHORITY30/07/2025
Mallika vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
amit jaiswal vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
Arun L vs ADI DEVELOPERScompletion of pending amenities along with BWSSB connection ,sanitation services and formation of associationAUTHORITY30/07/2025
Adarsh Shenoy vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
Polisetty Praveen Kumar vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
Patil Shreenivas vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
Satanarayana vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
Dhananjaya C vs ADI DEVELOPERSCompletion of pending amenities along with BWSSB connection and sanitation services and formation of association.AUTHORITY30/07/2025
Divakara P vs ADI DEVELOPERSDirections to Respondents. To Form Association, Complete handover process, Transfer Right and Title to Allottees, Pending dues to BWSSB and Pollution Control Board, Other Pending Amenities, Painting.AUTHORITY30/07/2025
ANSHUL TRIPATHI vs ADI DEVELOPERSCompletion of Pending Amenities along with BWSSB Connection and Sanitation services and formation of AssociationAUTHORITY30/07/2025
Dinesh Kumar Awasthi vs ADI DEVELOPERSCompletion of Pending Amenities along with BWSSB Connection and Sanitation services and formation of AssociationAUTHORITY30/07/2025
Vinod Kumar vs ADI DEVELOPERSCompletion of Pending Amenities along with BWSSB Connection and Sanitation services and formation of AssociationAUTHORITY30/07/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectT V SRINIVAS-1994HORAMAVU, BANAGALORE
ContractorSANJEEVI RAYUDU D-2006manjunatha layout, agrahara village
Structural engineerH S RAVI PRAKASH REDDY---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹18.9 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: STATE BANK OF INDIA bytarayanapura. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 6 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Outer Ring Road / Manyata6 km
MG Road / city centre13 km
Kempegowda Int'l Airport15 km
Bellandur–Marathahalli belt19 km
Whitefield IT hub20 km
Electronic City28 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Adi Developers.
Adi Developers has 2 projects registered in Bangalore.
30 complaints on the K-RERA register against Adi Developers in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Yelahanka

Major developers building in Yelahanka

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.