RERA Property Intelligence Report · Preview
Brigade Enterprises · Bengaluru North · K-RERA PRM/KA/RERA/1251/309/PR/070325/007559
The Drawings Report · ₹4,999
We read all 2 approved drawings and 35 filed papers on this project’s RERA file — the sheets the builder filed to get it approved.
437 of 1,124 flats not yet sold in the latest quarterly filing · 29% reported construction progress.
One real find, from a Noida project’s approved drawings: the buyer pays for 10,000 sq ft — the floor inside the flat is 6,982 sq ft.
Get it for this project →Not useful to your decision? Full refund — no questions asked. Sent as a PDF in one working day.
Free before you decide: the 14 things to get in writing before you book
Every item comes from a real RERA filing. Send it to the family group before anyone pays a token.
Send the checklist to the family group Read it here →Brigade Eternia, on 12.3 acres, has 1,124 units, with 880 three-bedroom, 116 one-bedroom, 16 two-bedroom, and 112 four-bedroom apartments, costing ₹906.5 crore. Its density of 91.7 homes per acre is the 72nd percentile among 521 Bengaluru North projects (median 75.3). Its declared completion date is 31 March 2030; no occupancy certificate is on record.
Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.
On the register
In context
Values as crawled from the official K-RERA record; context percentiles name their comparison population.
What you can verify free on this page
The official K-RERA filing record, in plain English
Registration and delivery
Brigade Eternia is registered with K-RERA as PRM/KA/RERA/1251/309/PR/070325/007559, and the promoter has declared completion for 31 Mar 2030.
31 Mar 2030
declared completion
Figures are the promoter's own filings as they stood when Quietlist last read the register. A declared completion date is a filing, not a handover commitment.
Source · K-RERA project register · read 10 Sep 2026
Project scale
Brigade Eternia spans 49,622 sq m (12.26 acres), comprises 12 towers, registers 1,124 units, and is declared to cost ₹906.49 cr.
₹906.49 cr
declared project cost
12.26acres
49,622 sq m
1,124units
on the registration
3.23FAR
sanctioned
Scale and cost as the promoter registered them. The declared cost is the promoter's own estimate on the filing, not a valuation and not a price to a buyer.
Source · K-RERA project registration · read 10 Sep 2026
Promoter record
Brigade is the promoter of record on 68 projects registered with K-RERA, 31 of which are past their declared completion dates on the register.
68projects
registered with K-RERA
31past declared date
on the register
74%
average construction reported
Counted across Quietlist's full K-RERA register store, matched on the promoter name as it appears on each filing.
Source · K-RERA register, all projects · read 10 Sep 2026
Construction
Brigade Eternia reports 29% construction progress in its most recent quarterly filing with K-RERA.
29%
reported construction progress
The percentage the promoter filed at the last quarterly report. It is a filed figure, not an inspection, and it can lag site conditions between filings.
Source · K-RERA quarterly progress report · read 10 Sep 2026
Sales
Brigade Eternia reports 686 of 1,124 units booked in its most recent quarterly filing with K-RERA, about 61%.
61%booked
686 of 1,124 units
Booked share as the promoter filed it at the last quarterly report; this is the filed position, not current availability.
Source · K-RERA quarterly progress report · read 10 Sep 2026
🔒 What I’d do as a buyer here · Drawings Report
The report opens with what this project really is — read from its approved drawings — then the specific calls: the cheapest good way to buy here, the flat to say no to, what you can stop worrying about, and what to get in writing before you sign anything.
Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Registered units | 1,124 | Total inventory registered with K-RERA. |
| Official carpet area | 123,463 sqm | Regulator-disclosed project-level carpet area, not vision-derived room sums. |
| Official built-up area | 258,993 sqm | Useful scale context when comparing density and project cost. |
| Registered land area | 49,622 sqm | The land area attached to this K-RERA registration. |
| Sanctioned FAR/FSI | 3.23 | Higher FAR generally means a denser vertical build, subject to site layout and open-space design. |
| Registered towers/wings | 12 | Official tower/wing count in the K-RERA detail page. |
| Parking disclosed | 1,206 total (1,381 covered, 131 open) — 1.07 spaces/unit | Confirm whether your quoted unit includes an allotted parking space and where it sits. |
| Approved plan number | BBMP/Addl.Dir/JDNORTH/0102/2024-25 | Use this to match the sanctioned drawing set shown by the builder. |
| Plan approval date | 04-03-2025 | |
| Project start date | 17-03-2025 |
K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.
Registered inventory mix
| Type | Units | Share | Official carpet area |
|---|---|---|---|
| 1 BHK | 112 | 10% | 41 sqm |
| 2 BHK | 2 | 0% | 80 sqm |
| 2 BHK | 2 | 0% | 77 sqm |
| 2 BHK | 2 | 0% | 76 sqm |
| 3 BHK | 2 | 0% | 126 sqm |
| 3 BHK | 82 | 7% | 126 sqm |
| 2 BHK | 2 | 0% | 91 sqm |
| 4 BHK | 30 | 3% | 160 sqm |
| 2 BHK | 2 | 0% | 74 sqm |
| 2 BHK | 2 | 0% | 88 sqm |
| 3 BHK | 14 | 1% | 94 sqm |
| 3 BHK | 42 | 4% | 113 sqm |
| 1 BHK | 2 | 0% | 46 sqm |
| 4 BHK | 22 | 2% | 175 sqm |
| 4 BHK | 60 | 5% | 175 sqm |
| 3 BHK | 189 | 17% | 115 sqm |
| 3 BHK | 14 | 1% | 104 sqm |
| 3 BHK | 110 | 10% | 103 sqm |
| 1 BHK | 2 | 0% | 48 sqm |
| 3 BHK | 15 | 1% | 115 sqm |
| 3 BHK | 41 | 4% | 139 sqm |
| 2 BHK | 4 | 0% | 71 sqm |
| 3 BHK | 181 | 16% | 101 sqm |
| 3 BHK | 133 | 12% | 113 sqm |
| 3 BHK | 57 | 5% | 111 sqm |
Registered tower / wing summary
| Tower/wing | Floors | Units | Parking | Height |
|---|---|---|---|---|
| Tower A | 13 | 126 | 126 | - |
| Tower B | 13 | 107 | 107 | - |
| Tower C | 13 | 117 | 117 | - |
| Tower D | 13 | 126 | 126 | - |
| Tower E | 14 | 90 | 90 | - |
| Tower F | 14 | 90 | 90 | - |
| Tower G | 14 | 90 | 90 | - |
| Tower H | 14 | 52 | 78 | - |
Showing first 8 of 12 tower/wing rows.
K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 1,124 official flat/unit rows, matching the 1,124 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.
By unit type
| Unit type | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| 3 BHK | 880 | 94.2-139.0 sqm | 36.1-54.5 sqm | 880 |
| 1 BHK | 116 | 41.3-47.7 sqm | 17.0-19.7 sqm | 116 |
| 4 BHK | 112 | 159.6-174.9 sqm | 65.8-71.0 sqm | 224 |
| 2 BHK | 16 | 70.9-91.0 sqm | 28.7-36.8 sqm | 16 |
By tower / wing
| Tower/wing | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| Tower A | 126 | 41.3-113.3 sqm | 17.0-46.9 sqm | 126 |
| Tower D | 126 | 41.3-114.6 sqm | 17.0-46.9 sqm | 126 |
| Tower C | 117 | 41.3-103.0 sqm | 17.0-40.1 sqm | 117 |
| Tower B | 107 | 41.3-104.1 sqm | 17.0-40.8 sqm | 107 |
| Tower E | 90 | 75.7-114.6 sqm | 30.4-46.9 sqm | 90 |
| Tower F | 90 | 47.7-115.3 sqm | 19.7-47.0 sqm | 90 |
| Tower G | 90 | 101.2-174.9 sqm | 39.4-71.0 sqm | 120 |
| Tower J | 90 | 77.1-174.9 sqm | 31.2-71.0 sqm | 120 |
| Tower K | 90 | 70.9-114.6 sqm | 28.7-46.9 sqm | 90 |
| Tower L | 90 | 70.9-114.6 sqm | 28.7-46.9 sqm | 90 |
| Tower I | 56 | 87.8-174.9 sqm | 35.3-71.0 sqm | 82 |
| Tower H | 52 | 125.9-174.9 sqm | 51.2-71.0 sqm | 78 |
| Unit | Tower | Floor | Type | Carpet | UDS | Parking |
|---|---|---|---|---|---|---|
| A 0001 | Tower A | 0 | 3 BHK | 113.3 sqm | 46.9 sqm | 1 |
| A 0002 | Tower A | 0 | 3 BHK | 113.3 sqm | 46.9 sqm | 1 |
| A 0003 | Tower A | 0 | 3 BHK | 101.2 sqm | 39.4 sqm | 1 |
| A 0004 | Tower A | 0 | 1 BHK | 46.4 sqm | 19.5 sqm | 1 |
| A 0005 | Tower A | 0 | 3 BHK | 101.2 sqm | 39.4 sqm | 1 |
| A 0006 | Tower A | 0 | 3 BHK | 101.2 sqm | 39.4 sqm | 1 |
What the numbers tell you
Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.
🔒 Which flat to ask for · Drawings Report
The flat-level read: which towers and floors to prefer and which to avoid, what the drawings put above, below and beside each flat, and the things on this site nobody at the sales desk will tell you about.
⚠ 1 litigation case on record
7 of 35 compliance document slots are filed as Not Applicable; the remaining 28 slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)
| Parties | Relief sought | Disposal | Order date |
|---|---|---|---|
| Rajath Seshadri Yelahanka vs Brigade Eternia | I seek my 4,62,251 to be refunded. plus delay penalty of 50,000 | AUTHORITY | 09/09/2025 |
⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.
Complaints on this project's K-RERA page (21 complaints listed against this promoter)
| Complaint | Subject (as filed) | Project | Status |
|---|---|---|---|
| CMP/190802/0003774 02-08-2019 | Project delay compensation & Veracity of the agreement & Brochure while booking | Brigade Panorama (another project by this promoter) | DISPOSED AO |
| CMP/190915/0004196 15-09-2019 | Waiting period more than 1.5 years, amenities built on kharab land, Club house not as per agreement | Brigade Panorama (another project by this promoter) | DISPOSED AO |
| CMP/190920/0004245 20-09-2019 | Delay in paying the Delay Compensation | Brigade Panorama (another project by this promoter) | DISPOSED AO |
| CMP/200211/0005414 11-02-2020 | Brigade group not given the compensation as per RERA and changes in the layout plan | Brigade Panorama (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/200513/0005880 13-05-2020 | Refund of amount due to delay in registration/handover | Brigade Panorama (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/201130/0007159 30-11-2020 | Brigade has backed out of delay compensation payment after earlier assuring to pay the same | Brigade Panorama (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/210212/0007498 12-02-2021 | Recovery of delay compensation, rental loss & Property tax amount with Interest for 6 years of delay caused by builder to deliver possession of flat | Plumeria Lifestyle at Brigade Meadows (another project by this promoter) | DISPOSED AUTHORITY BENCH4 |
| CMP/210512/0007948 12-05-2021 | BUILDER NOT ALLOWING INSPECTION OF OUR APARTMENT | Brigade Buena Vista-Phase 2 (another project by this promoter) | DISPOSED AUTHORITY BENCH4 |
Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.
Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.
4 further authority slots are marked not applicable by the regulator.
| Authority / NOC | Status | Date | File |
|---|---|---|---|
| Water supply and sewage board | Approved | 27-05-2024 | Brigade Eternia BWSSB NOC.pdf |
| KSPCB- PCB (10 Acres to 125 Acres) | Approved | 25-07-2024 | Brigade Eternia Consent for Establishment 1.pdf |
| KSPCB- MOEF (Above 50 Acres) | Approved | 24-07-2024 | Brigade Eternia Environmental Clearance1.pdf |
| KPTCL- BESCOM | Approved | 20-08-2024 | Brigade Eternia BESCOM.pdf |
| Fire and Safety | Approved | 05-11-2024 | Brigade Eternia Fire NOC.pdf |
| Airport Authority of India | Approved | 11-09-2023 | Brigade Eternia AAI NOC.pdf |
K-RERA names 5 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Chartered accountant | R. Srinivasan | 28986 | 2000 | Bengaluru Urban, Karnataka - 560003 |
| Engineer | Suhas M | BCC/BL-3.6/SE-314/2022-23 | 2007 | Bengaluru Urban, Karnataka - 560003 |
| Engineer | VIJAY KUMAR S B | BCCL/BL-3.6/SE-0041/2024-25 | 2000 | Bengaluru Urban, Karnataka - 560072 |
| Architect | TILAK THOMAS | CA/99/25282 | 1992 | Bengaluru Urban, Karnataka - 560001 |
| Contractor | Brigade Inhouse | - | 1986 | Bengaluru Urban, Karnataka - 560055 |
Brigade has 68 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Brigade Enterprises”) (average reported construction progress 74%). 31 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.
Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.
Latest quarterly filing (2026-Q1): ₹126.03 Cr collected from buyers, ₹97.57 Cr withdrawn from the project's escrow account.
| Construction progress | 21% → 29% (+8 pts) |
| Units sold/booked as registered | 687/1124 (61%) |
| Buyer collections in available QPRs | ₹413.91 Cr |
| Escrow withdrawals in available QPRs | ₹237.56 Cr (0.57x collections) |
QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.
Declared construction cost ÷ registered units averages to ₹80.6 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.
RERA 70% project account is on file: KOTAK MAHINDRA BANK Lavelle Road, Bangalore IFSC Code : KKBK0000422 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Outer Ring Road / Manyata | 7 km |
| MG Road / city centre | 14 km |
| Kempegowda Int'l Airport | 17 km |
| Bellandur–Marathahalli belt | 21 km |
| Whitefield IT hub | 22 km |
| Electronic City | 29 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
The approved drawings
Everything above is on this page already, free, from the government record. The drawings are different: the 2 approved sheets are the same drawings the builder filed to get Brigade Eternia approved — what sits under each tower, which floor holds machines, what the sales sheet leaves out. Nobody reads them for you. We do.
What that turns up — from other projects’ filings:
ATS Knightsbridge · Sector 124, Noida
You pay for 10,000 sq ft. The floor inside your home is 6,982 sq ft. The rest is walls, shared circulation and services. Get both numbers written into your agreement before you pay any booking amount.
Oberoi Elysian · Goregaon East, Mumbai
“The building is complete.” The tower has reached full height — true. The same filed certificate, same page: sanitary fittings 6% done. Ask for a possession date in writing.
Godrej Aristocrat · Sector 49, Gurugram
Paying extra for the top floor? The terrace drawing shows what sits on the slab above those flats: the overhead water tanks, the lift machine rooms and the roof machinery. Ask which flat sits under which.
Prestige Camden Gardens · Thanisandra, Bengaluru
The approved parking table asks for 12 visitor spaces. It shows 0. Two-wheeler spaces: also 0. Ask in writing where visitors will park.
Want this project read from its filed drawings?
437 of the 1,124 flats are not yet sold in the latest quarterly filing, so which one you take is a real choice. With 29% reported construction progress, there is no finished building to walk through — the approved drawings are the only place to see what you are buying. We read the 2 approved drawings on Brigade Eternia’s file and tell you which flats we would ask for, what sits around them, and what to get in writing before you pay the token.
This page is the free K-RERA filing summary. For Brigade Eternia, one reading of it goes further. Which flat should I ask for? — what the approved drawings and filed papers say about the flats, the parking, the approvals, and what to get in writing before you sign. That is the Drawings Report. See a real one first:
Drawings Report sample: Prestige Camden Gardens → · browse all sample reports →
Payment is confirmed automatically. The Drawings Report is 1 working day. We email the link, so you can close the tab.
Drawings Report · ₹4,999
Every drawing on file, read — which flat to ask for · 1 working day
Not useful to your decision? Full refund — no questions asked.
Paying from outside India? Pay $59 (Drawings Report) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.
Built by Brigade Enterprises. View Brigade Enterprises's full track record →
Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.