Surabhi Layout

· Ningegowda D

Is this the right project?
Which plot should you choose?

Read the free RERA facts below. For help choosing a plot or comparing a price, select a report.

See the report before you buy

Avoid bad decisions, only go for the best plots.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
100%construction reportedQ3 2025 filing

Free project details

Registration read 16 Jul 2026

Construction progress and dates

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q3 2025

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 16 Jul 2026

RERA details for Surabhi Layout

K-RERA · PRM/KA/RERA/1267/377/PR/040325/007543

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Approved plan numberMan.Na.Pra/Na.Yo.Vi/Vi.Na/45/2023-24Use this to match the sanctioned drawing set shown by the builder.
Plan approval date06-11-2023
Project start date01-12-2023

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

6 of 19 compliance document slots are filed as Not Applicable; the remaining 13 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2025 — which has passed with no OC on file.

See the filed approval statuses and linked documents →

Statutory approval status

RERA filing

3 of 3 applicable approvals are marked Approved in the filing. Check the linked documents for their scope and validity.

8 further authority slots are marked not applicable in the filing.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved13-11-2024Water board completion Report SuL.pdf
KPTCL- BESCOMApproved07-11-2024Chescom Completion Report SuL.pdf
Horticulture departmentApproved08-11-2024Horticulture Dept NOC SuL.pdf

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantLokanath B J2601972021Mysore, Karnataka - 570004
EngineerNagaraja BMYS/BL/10620/24-252024Mysore, Karnataka - 570028

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q3): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress100% → 100% (+0 pts)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: HDFC Mandya IFSC Code : HDFC0002567 Pin Code : 571401. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 89 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Electronic City89 km
MG Road / city centre90 km
Outer Ring Road / Manyata95 km
Bellandur–Marathahalli belt96 km
Whitefield IT hub104 km
Kempegowda Int'l Airport113 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Ningegowda.

Other RERA-registered projects in Yelahanka

Major developers building in Yelahanka

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 16 Jul 2026. Document and inventory dates are shown in their sections.