RERA Property Intelligence Report · Preview

URBANEST ELITE 35

URBANEST REALTY · Bengaluru East · K-RERA PRM/KA/RERA/1251/446/PR/050224/006610

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
3
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

35
Registered units
₹7.3 Cr
Est. construction cost
Units profiled
37
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units35Total inventory registered with K-RERA.
Official carpet area3,285 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area5,628 sqmUseful scale context when comparing density and project cost.
Registered land area1,921 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.74Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings1Official tower/wing count in the K-RERA detail page.
Parking disclosed35 total (35 covered, 0 open) — 1.00 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Approved plan number353/2023-24Use this to match the sanctioned drawing set shown by the builder.
Plan approval date13-09-2023
Project start date10-10-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK Flats35100%3,285 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
URBANEST ELITE 356353520.65 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 35 official flat/unit rows, matching the 35 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK3581.0-106.8 sqm46.5-66.5 sqm35

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
URBANEST ELITE 353581.0-106.8 sqm46.5-66.5 sqm35
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
G-001URBANEST ELITE 3503 BHK83.7 sqm48.0 sqm1
G-002URBANEST ELITE 3503 BHK99.0 sqm56.8 sqm1
G-003URBANEST ELITE 3503 BHK95.5 sqm54.7 sqm1
G-004URBANEST ELITE 3503 BHK100.6 sqm57.7 sqm1
G-005URBANEST ELITE 3503 BHK81.0 sqm46.5 sqm1
F-101URBANEST ELITE 3513 BHK88.4 sqm50.7 sqm1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~1,010 sqft — mid-format homes (2–3BHK territory), not compact stock. This is a boutique, low-density project — 35 homes across 1 tower. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 35 parking spaces for 35 homes (~1.0 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~58 sqm per home; across all 35 homes that is ~105% of the plot — a healthy sign: buyers collectively hold close to all the land. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.
Joint-development titleThis is (at least partly) a joint-development (JDA) project — the landowner and developer split the built units per an agreed ratio. Standard in Bengaluru, but it adds one check: confirm in writing that your specific unit falls in the developer's sale share, and ask to see the JDA's area-sharing clause so there's no dispute over who can sell you the flat.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

5 of 30 compliance document slots are filed as Not Applicable; the remaining 25 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

6 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved20-02-2023Water NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved25-05-2023KSPCB NOC.pdf
KPTCL- BESCOMApproved17-06-2023BESCOM NOC.pdf
Fire and SafetyApproved25-07-2023Fire NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantUtpala Sri Karan022542S2019Nellore, Andhra Pradesh - 524002
EngineerPralabhi Associates Y BhaskarBCC/BL-3.6/SE-0315/2019-202019Bengaluru Urban, Karnataka - 560038
ArchitectRaghavendra SCA/2009/459092009Bengaluru Urban, Karnataka - 560085
ContractorURBANEST REALTY-2018Bengaluru Urban, Karnataka - 560036

Builder track record

RERA filing

Urbanest Realty has 3 other K-RERA-registered projects in our records (average reported construction progress 51%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress98% → 100% (+2 pts)
Units sold/booked as registered19/35 (54%)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹20.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC RAMAMURTHY NAGAR IFSC Code : HDFC0002779 Pin Code : 560016. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Whitefield IT hub12 km
Outer Ring Road / Manyata14 km
Kempegowda Int'l Airport14 km
Bellandur–Marathahalli belt16 km
MG Road / city centre18 km
Electronic City27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Urbanest Realty.
Urbanest Realty has 4 projects registered in Bangalore, 1 completed.

Other projects by this builder in Bangalore

East Field
Filing overdue · 30% built · 32% sold
East Field
Filing overdue · 30% built · 32% sold
Serene Exotica
Filing overdue · 94% built

Other RERA-registered projects in Krishnarajapuram

Trifecta Verdeen Resplandor ROW House Phase-3

Major developers building in Krishnarajapuram

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Urbanest Elite 35?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 27 Jul 2026