Bangalore/Project record

K-RERA · the public record

Nikoo Homes II East

Bengaluru North · Bhartiya Urban

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
30 Jun 2021declared completionK-RERA registration · read 26 Oct 2026
1,203registered unitsK-RERA registration · read 26 Oct 2026

Free project details

Registration read 26 Oct 2026

Registered units and project size

As per Annexure
0

Filed categories, unchanged · K-RERA registration · read 26 Oct 2026

The whole registration

8.5registered acres

142.1registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for Nikoo Homes II East

K-RERA · PRM/KA/RERA/1251/309/PR/171014/000197

Project facts and comparisons

On the register

Declared completion30 June 2021
Land area34,249 sq m (8.5 acres)
Homes registered1,203
Tower/wing entries6

In context

Density142.1 homes per acre
Density in context95th percentile of 529 Bengaluru North projects (median 75.3)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units1,203Total inventory registered with K-RERA.
Registered land area34,249 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI5.14Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries6Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)1,260Separate filed counts; these categories may overlap and are not added together.
Open-parking field80Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date31-08-2015

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
As per Annexure00 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A33245249-
B`33244248-
C33260263-
D33245278-
E159898-
F15111124-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 1,203 official flat/unit rows, matching the 1,203 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK48759.3-67.1 sqm16.3-19.6 sqm487
3BHK32488.1-102.8 sqm23.6-28.8 sqm324
2BHK+STUDY14477.6-85.6 sqm20.8-25.0 sqm144
3BHK+STUDY60111.4-111.6 sqm29.2-31.1 sqm60
1BHK4539.1-41.9 sqm10.9-11.5 sqm45
1BHK+STUDY4552.4-53.8 sqm15.8-16.0 sqm45
4BHK+STAFF45144.3-160.7 sqm39.8-45.0 sqm90
STUDIO2630.3-32.6 sqm8.2-8.9 sqm26
Loft15113.0-131.6 sqm34.2-39.1 sqm15
Sky Villa11157.1-204.6 sqm47.4-58.6 sqm22
Skyvilla1202.3 sqm57.8 sqm2

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
C26052.4-202.7 sqm15.8-58.2 sqm263
A24559.3-204.6 sqm16.3-57.4 sqm249
D24540.7-202.3 sqm11.2-57.8 sqm278
B`24439.1-203.4 sqm10.9-58.6 sqm248
F11130.3-160.7 sqm8.2-45.0 sqm124
E9859.3-94.0 sqm17.9-27.3 sqm98
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A101A13BHK+STUDY111.6 sqm31.0 sqm1
A102A12BHK60.4 sqm16.3 sqm1
A103A12BHK59.3 sqm17.4 sqm1
A104A13BHK93.9 sqm26.3 sqm1
A105A13BHK94.6 sqm26.6 sqm1
A106A12BHK65.6 sqm19.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

Litigation status was not supplied in the captured record. This is not confirmation that there are no cases.

All 37 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Jun 2021, extended (Covid Extension) to 30 Dec 2021 — both dates have passed with no OC on file.

Approval documents

Electricity (BESCOM/ESCOM)Bundled document listed: All NOCs from Authority
Water & sewage (BWSSB/KWSSB)Bundled document listed: All NOCs from Authority
Fire NOCBundled document listed: All NOCs from Authority
Pollution control (KSPCB)Bundled document listed: All NOCs from Authority
Environmental clearanceBundled document listed: All NOCs from Authority
Airport Authority height clearanceBundled document listed: All NOCs from Authority

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
YASHASWINI SEVANTH vs NIKOO HOMES II EASTNEED Complete refund with interest cause of false commitment , and not providing PMAY scheme.forced to sign the agreemnt in 10 min,without even readingAUTHORITY27/07/2022

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (11 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190215/0002134
15-02-2019
Inferiror unusable car park allotement, betrayal of trust, delay compensation, GST benefits not transferred to customers, unaddressed quality issuesNikoo Homes I (Towers 1 - 6 & 10) (another project by this promoter)DISPOSED AO
CMP/191118/0004752
18-11-2019
Non-Payment/denial of Refund of advance amount after cancellation of bookingBhartiya Leela Residences (another project by this promoter)DISPOSED AO
CMP/191203/0004833
03-12-2019
Interest against pending paymentNikoo Homes I (Towers 1 - 6 & 10) (another project by this promoter)DISPOSED AO
CMP/200225/0005545
25-02-2020
Delay CompensationNikoo Homes I (Towers 1 - 6 & 10) (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/200611/0006015
11-06-2020
Delay CompensationNikoo Homes I (Towers 1 - 6 & 10) (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/200726/0006254
26-07-2020
Builder trying to cancel apartment due to non-payment if dues in old terms before rera registeredNikoo Homes II West (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/200731/0006278
31-07-2020
Carpet area is delivered lessNikoo Homes I (Towers 1 - 6 & 10) (another project by this promoter)DISPOSED AO
CMP/200909/0006547
09-09-2020
Delay CompensationNikoo Homes I (Towers 1 - 6 & 10) (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectRSP Design Consultants India Pvt Ltd.-1997Museum Road, Bengaluru
ContractorUrbanac Projects Pvt Ltd-20084th Main, Hebbal
Structural engineerInnotech Engineering Consult Pvt Ltd---

Builder track record

RERA filing

Bhartiya Urban has 15 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Bhartiya Urban”) (average reported construction progress 55%). 3 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹56.8 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: Bank of Baroda K G Road Main Branch (IFSC BARB0BANGAL, a/c …1474). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest of the listed job hubs is about 5 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Outer Ring Road / Manyata5 km
MG Road / city centre12 km
Kempegowda Int'l Airport15 km
Bellandur–Marathahalli belt17 km
Whitefield IT hub17 km
Electronic City26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Bhartiya Urban. View Bhartiya Urban's full track record →
Bhartiya Urban has 15 projects registered in Bangalore, 1 completed.
5 complaints on the K-RERA register against Bhartiya Urban in Bangalore.

Other projects by this builder in Bangalore

Bhartiya Garden Estate Phase-1
Filing overdue · 38% built · 87% sold
Bhartiya Garden Estate Phase-2
Filing overdue · 41% built · 75% sold
Bhartiya Garden Estate Phase-3
Filing overdue · 42% built · 52% sold
Nikoo Homes 8, Bhartiya Garden Enclave, Phase-1
Filing overdue · 38% built · 21% sold
Nikoo Homes 8, Bhartiya Garden Enclave, Phase-2
Filing overdue · 46% built · 0% sold
Nikoo Homes IV
Filing overdue · 100% built · 100% sold

Other RERA-registered projects in Yelahanka

Major developers building in Yelahanka

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 26 Oct 2026. Document and inventory dates are shown in their sections.