RERA Property Intelligence Report · Preview

SLV GOLDEN TOWERS

SLV Developers · Bengaluru North · K-RERA PRM/KA/RERA/1251/309/PR/051024/007131

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
9
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

242
Registered units
₹85.0 Cr
Est. construction cost
Units profiled
41
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units242Total inventory registered with K-RERA.
Official carpet area27,739 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area38,586 sqmUseful scale context when comparing density and project cost.
Registered land area12,646 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings2Official tower/wing count in the K-RERA detail page.
Parking disclosed242 total (273 covered, 0 open) — 1.00 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Approved plan numberBBMP/Addl.Dir/JDNORTH01019/22-23Use this to match the sanctioned drawing set shown by the builder.
Plan approval date09-11-2023
Project start date01-07-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
4 BHK229%2,984 sqm
3 BHK15464%15,478 sqm
2.5 BHK115%934 sqm
2 BHK5523%3,976 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
SLV KINGDOM BLOCK A1012112136.6 m
SLV KINGDOM BLOCK B1012112136.6 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 242 official flat/unit rows, matching the 242 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK15491.6-108.5 sqm48.0-59.2 sqm154
2 BHK5570.5-79.3 sqm37.0-43.3 sqm55
4 BHK22135.6 sqm71.2 sqm22
2.5 BHK1184.8 sqm46.2 sqm11

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
SLV KINGDOM BLOCK A12179.3-135.6 sqm41.6-71.2 sqm121
SLV KINGDOM BLOCK B12170.5-101.7 sqm37.0-55.5 sqm121
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
G12SLV KINGDOM BLOCK A03 BHK101.7 sqm53.4 sqm1
G13SLV KINGDOM BLOCK A02 BHK79.3 sqm43.3 sqm1
G14SLV KINGDOM BLOCK A03 BHK91.6 sqm49.9 sqm1
G15SLV KINGDOM BLOCK A03 BHK108.5 sqm56.9 sqm1
G16SLV KINGDOM BLOCK A04 BHK135.6 sqm71.2 sqm1
G17SLV KINGDOM BLOCK A04 BHK135.6 sqm71.2 sqm1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~1,040 sqft — mid-format homes (2–3BHK territory), not compact stock. This is a mid-scale project — 242 homes across 2 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 242 parking spaces for 242 homes (~1.0 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~51 sqm per home; across all 242 homes that is ~98% of the plot — a healthy sign: buyers collectively hold close to all the land. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 34 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC and environmental clearance are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

8 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved12-12-2022BWSSB NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved02-09-2023CFE.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantIVSS Raju2182822015Bengaluru Urban, Karnataka - 560095
EngineerIragsavarapu Madhava Rao20TP10/GHMC2010Hyderabad, Telangana - 500033
ArchitectAzgar Ali ShariffCA/2012/576052012Hyderabad, Telangana - 500044
ContractorAzgar Ali Shariff-2012Hyderabad, Telangana - 500033

Builder track record

RERA filing

Slv Developers has 9 other K-RERA-registered projects in our records. 5 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q3): ₹12.24 Cr collected from buyers, ₹18.39 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹18.39 Cr) exceeded buyer collections (₹12.24 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress21% → 21% (+0 pts)
Units sold/booked as registered28/242 (12%)
Buyer collections in available QPRs₹12.24 Cr
Escrow withdrawals in available QPRs₹18.39 Cr (1.50x collections)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹35.1 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Yelahanka Old Town IFSC Code : HDFC0000371 Pin Code : 560064. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata8 km
Kempegowda Int'l Airport14 km
MG Road / city centre16 km
Bellandur–Marathahalli belt22 km
Whitefield IT hub22 km
Electronic City31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Slv Developers. View Slv Developers's full track record →
Slv Developers has 9 projects registered in Bangalore.
1 complaints on the K-RERA register against Slv Developers in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Yelahanka

Major developers building in Yelahanka

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.