Unishire Palazzo

Bengaluru North · UNISHIRE SKYSCAPES

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
31 Jul 2022declared completionK-RERA registration · read 25 Oct 2026
0registered unitsK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Registered units and project size

2, 3 & 4 BHK
52

Filed categories, unchanged · K-RERA registration · read 25 Oct 2026

The whole registration

1.2registered acres

0.0registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for Unishire Palazzo

K-RERA · PRM/KA/RERA/1251/309/PR/180516/001679

Project facts and comparisons

On the register

Declared completion31 July 2022
Land area4,849 sq m (1.2 acres)
Unit mix52 × 2, 3 & 4 BHK

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Official carpet area10,409 sqmTotal carpet area reported for the project.
Registered land area4,849 sqmThe land area attached to this K-RERA registration.
Parking total (reconciled)54Separate filed counts; these categories may overlap and are not added together.
Open-parking field54Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date19-08-2014

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2, 3 & 4 BHK52100%10,409 sqm

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

Litigation status was not supplied in the captured record. This is not confirmation that there are no cases.

All 25 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Jul 2022, extended (Covid Extension) to 30 Apr 2023 — both dates have passed with no OC on file.

Approval documents

Electricity (BESCOM/ESCOM)Bundled document listed: All NOCs from Authority
Water & sewage (BWSSB/KWSSB)Bundled document listed: All NOCs from Authority
Fire NOCBundled document listed: All NOCs from Authority
Pollution control (KSPCB)Bundled document listed: All NOCs from Authority
Environmental clearanceBundled document listed: All NOCs from Authority
Airport Authority height clearanceBundled document listed: All NOCs from Authority

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (2 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
B K Lalitha vs UNISHIRE PALAZZOCancel the RERA registration for this project, please do not entertain the extension if requested for the above mentioned reasons and hand over the land back to the land owners.AUTHORITY11/04/2025
B.K.Srinivas vs Unishire PalazzoObjection towards granting approvaLAUTHORITY11/03/2024

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (18 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190502/0002853
02-05-2019
Delay in delivering the projectUnishire Premia (another project by this promoter)DISPOSED AO
CMP/191225/0005040
25-12-2019
MORE THAN THREE YEARS DELAY IN DELIVERING FLATS, COLLUSION BETWEEN PROMOTER AND LENDER RELIANCE NIPPONUnishire Premia (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/200101/0005110
01-01-2020
MORE THAN THREE YEARS DELAY IN DELIVERING FLATS, COLLUSION BETWEEN PROMOTER AND LENDER RELIANCE NIPPONUnishire Premia (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/200102/0005080
02-01-2020
MORE THAN THREE YEARS DELAY IN DELIVERING FLATS, COLLUSION BETWEEN PROMOTER AND LENDER RELIANCE NIPPONUnishire Premia (another project by this promoter)DISPOSED AO
CMP/200102/0005123
02-01-2020
More than three years delay in delivering flats, collusion between promoter and lender Reliance NipponUnishire Premia (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/200104/0005136
04-01-2020
MORE THAN THREE YEARS DELAY IN DELIVERING FLATS, COLLUSION BETWEEN PROMOTER AND LENDER RELIANCE NIPPONUnishire Premia (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/200105/0005143
05-01-2020
MORE THAN THREE YEARS DELAY IN DELIVERING FLATS, COLLUSION BETWEEN PROMOTER AND LENDER RELIANCE NIPPONUnishire Premia (another project by this promoter)DISPOSED AUTHORITY
CMP/200107/0005160
07-01-2020
COMPLETION OF THE PROJECT AND NOT MEET THE DELIVERY DATESUnishire Premia (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectAslam Architects-2006Cunnigham Road, Bangalore
ContractorSafalaakar Builtech LLP-2015Nehru Nagar, Kumarapark WEST Bangalore
Structural engineerMr.Manohar---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: ICICI Bank Kumarapark (IFSC ICIC0006253, a/c …0043). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 3 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Outer Ring Road / Manyata3 km
MG Road / city centre11 km
Kempegowda Int'l Airport17 km
Bellandur–Marathahalli belt17 km
Whitefield IT hub18 km
Electronic City26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Unishire Skyscapes.
Unishire Skyscapes has 2 projects registered in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Yelahanka

Major developers building in Yelahanka

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.