Grande Ventila Phase 2 Wing A

Wagholi · Satav Developer and Builders

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Sep 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Grande Ventila Phase 2 Wing A

MahaRERA · P52100007429

Delivery and registration

When is the project declared for completion?

Grande Ventila Phase 2 Wing A is registered with MahaRERA as P52100007429 and the promoter has declared completion for 30 Sep 2023.

30 Sep 2023

declared completion

37months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100007429
Registered on17 Aug 2017
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 37 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Grande Ventila Phase 2 Wing A record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Grande Ventila Phase 2 Wing A in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
Grande Ventila Wing A1G+1230 Sep 2019

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Grande Ventila Phase 2 Wing A, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC1240127529/12/2024Avinish Ashok Shinde vs grandeventilla grandeventillaorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Filed descriptions (status fields empty): 1 “Pending”. These are the promoter's filed statements, not a current court check. A disposed application or motion does not establish that the whole case is closed. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your unit. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Cjsd Pune9012011Status not supplied
Filed description: Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered29 Sep 20201) Construction industry is highly dependent on manual labour. Due to Lok Sabha election in apr-may'19, many of the labourers moved to their native states and hence there was an a
29 Sep 202031 Mar 2022Due to after effect of COVID pandemic, labor force, necessary for carrying out construction activity, still havent returned back to active duty from their native places. With the c
31 Mar 202230 Sep 2023Due to after effect of COVID pandemic, labor force, necessary for carrying out construction activity, still havent returned back to active duty from their native places. With the c

Location, Land & Connectivity

Located at Wagholi, Wagholi, Haveli, Pune, 412207. Per the filed land record, the plot is bounded to the north by By Gat No 1141 Part, to the south by By Gat No 1139, to the east by By Gat No 1142P Part and to the west by By Gat No 1141 Part. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 5 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Kharadi / EON IT Park5 km
Pune Int'l Airport (Lohegaon)7 km
Magarpatta / Hadapsar IT9 km
Pune Junction / city centre13 km
Baner–Balewadi belt22 km
Hinjewadi Rajiv Gandhi IT Park26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wagholi

Kharadi Pune Phase I - Tower 1 To 4
declared completion Oct 2026 · Lodha Developers Limited
Defence Colony Pune Phase4
declared completion Nov 2026 · Defence Colony Pune
Sai Shawas
declared completion Dec 2026 · Vilas Tukaram Wadghule
Panchshil Towers
declared completion Dec 2026 · Panchshil Infrastructure Holdings Pvt. L
Soho
declared completion Dec 2026 · Panchshil Infrastructure Holdings Pvt. L
White Stone A Bldg
Not filing quarterly progress reports · declared completion Dec 2026 · Kashinath Sopan Dabhade
More builders in Wagholi

Major developers building in Wagholi

More projects in Pune

Other RERA-registered projects in Pune

Grande View 7 Capital
declared completion Dec 2024 · Chirag Developers
Grande View 7 Phase III Building K
declared completion Dec 2021 · Chirag Developers
Grande View 7 Phase IV Building F&G
declared completion Jan 2022 · Chirag Developers
Grande View7 Phase VI Buiding I
declared completion Jun 2026 · Chirag Developers
Grant Bay
declared completion Dec 2026 · Gagan Landmarks LLP
Gravity
declared completion Dec 2018 · Bhujbal Brothers Construction Company

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.