Pune/Project record

MahaRERA · the public record

Shree Sai Hills Phase I

Pune · Shree Sai Hills

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2021declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Shree Sai Hills Phase I

MahaRERA · P52100004887

Delivery and registration

When is the project declared for completion?

Shree Sai Hills Phase I is registered with MahaRERA as P52100004887 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

58months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100004887
Registered on09 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 58 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Shree Sai Hills Phase I record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

Shree Sai Hills is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Shree Sai Hills Phase I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
A1G+731 Dec 2019
B1G+631 Dec 2019
C1G+731 Dec 2019

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for Shree Sai Hills Phase I, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000002345119/09/2019Mr. Sakharam Raghunath Kolhatkar vs Shree Sai Hills through its partner a) Mrs. Jayashree M Gaikwad b) Mohan P Gaikwadorder passed
CC00500000014721611/06/2022Sakharam Raghunath Kolhatkar vs Shree Sai Hills Through its Partners a)Mrs. Jayashri Mohan Gaikwad b)Mr. Mohan Pandharinath Gaikwadorder passed
CC00500000010681223/03/2022MAYANK RAINA vs M/S SHREE SAI HILLSorder passed
CC00500000017788010/12/2022Sachin Nandkumar Zunzar vs SHREE SAI HILLSorder passed
CC00500000047146606/08/2024MAYANK RAINA vs M/S SHREE SAI HILLSorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020Dear sir This is with regards to our project called Shree Sai Hills which is situated at Gat no.79 Kesnand Taluka Haveli District Pune-412207. I would like to request to give

Location, Land & Connectivity

Located at Pune City, Pune, 412207. Per the filed land record, the plot is bounded to the north by Gat No 81, to the south by Gat No 87, to the east by Vitthal Shinde Land Gat no 79 and to the west by Gat No 91. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 9 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Kharadi / EON IT Park9 km
Pune Int'l Airport (Lohegaon)10 km
Magarpatta / Hadapsar IT12 km
Pune Junction / city centre16 km
Baner–Balewadi belt25 km
Hinjewadi Rajiv Gandhi IT Park29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wagholi

Kharadi Pune Phase I - Tower 1 To 4
declared completion Oct 2026 · Lodha Developers Limited
Defence Colony Pune Phase4
declared completion Nov 2026 · Defence Colony Pune
Sai Shawas
declared completion Dec 2026 · Vilas Tukaram Wadghule
Panchshil Towers
declared completion Dec 2026 · Panchshil Infrastructure Holdings Pvt. L
Soho
declared completion Dec 2026 · Panchshil Infrastructure Holdings Pvt. L
White Stone A Bldg
Not filing quarterly progress reports · declared completion Dec 2026 · Kashinath Sopan Dabhade
More builders in Wagholi

Major developers building in Wagholi

More projects in Pune

Other RERA-registered projects in Pune

Shree Sai Hills Phase II
declared completion Dec 2025 · Shree Sai Hills
Shree SAI Sahwas
declared completion Dec 2030 · Anuradha Landline AND Housing Developers
Shree Samarth
declared completion Dec 2022 · Lalit Parmeshwar Thore
Shree Samarth Residency
declared completion Mar 2018 · M/s. Dampdar Pote And Associates
Shree Samarth Shrushti
declared completion Sep 2026 · Jagdamba Developers
Shree Samartha Daffodils
declared completion Mar 2027 · Shree Samartha Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.